O-Train To Close At Times in Sept., Oct.

The purpose of this memo is to inform the Mayor and Members of Council of service adjustments required on O-Train Line 1 in September and early October.

August O-Train Line 1 Work


As outlined in the memo of August 5, O-Train Line 1 operations will begin at noon on Sunday,  August 31. This will allow for Stage 2 East Extension integration activities. R1 bus service will  operate between Tunney’s Pasture and Blair stations during the planned closure.

This is a release from the City of Ottawa.

OC Transpo staff will be at key locations to support customers during their trips, and notifications  are being shared through social media, text messages, and alerts on octranspo.com. Customers  are encouraged to use the Travel Planner or Transit app to plan their trips.

>



O-Train East Extension Performance Test

The successful completion of integration activities on August 31 will allow performance testing to  be conducted on the entire system between Tunney’s Pasture and Trim stations on September  13 to 14. This milestone involves confirming that the integrated system can achieve the expected  service levels upon public launch and in the future, as outlined in the Project Agreement.

For customers, this means that on September 13 and 14:

• Line 1 service will not operate between Tunney’s Pasture and Blair stations. • R1 Bus service will run between Tunney’s Pasture and Blair stations.

• Shuttle bus service will run between St-Laurent and Cyrville stations.

• Customers may see out-of-service trains during regular service hours while tests take place.

Further information regarding this work will be provided at the Transit Committee meeting on  September 11.

During the same weekend, OC Transpo and Infrastructure and Water Services Department  (IWSD) will continue the work identified as part of the Ontario Structure Inspection Manual  (OSIM) inspections in the St-Laurent tunnel. Coordination of this necessary work with other  activities further minimizes the number of disruptions to customers.

September and October O-Train Line 1 Maintenance Work

Rideau Transit Maintenance (RTM) will be conducting maintenance work from September 26 to  October 5 to continue to ensure long-term sustainability and improvements to the service  reliability of Line 1. OC Transpo and RTM have worked collaboratively to reduce the impacts to  customers and minimize disruptions wherever possible, including after the East Extension is open  to the public.

For customers this means that:

• Line 1 will not operate after 8 pm on September 26, and R1 will run between Tunney’s  Pasture and Blair stations.

• Line 1 service will only be available at one platform at some stations after 11:30 pm on  September 27 and 29 to October 2.

• Line 1 will not operate on October 4 and 5, and R1 will run between Tunney’s Pasture and  Blair stations.

During this time, RTM will conduct various activities including:

• Rail replacement between Rideau and uOttawa stations.

• Rail grinding across the entire system.

• Ongoing upgrades of supporting cables (parafils) of the overhead catenary system, to  make them more resilient and durable.

• General station maintenance and seasonal cleaning.

Customers are encouraged to use the Travel Planner and Transit app to plan their trips.  Customers can also visit octranspo.com for travel planning assistance or call 613-560-5000. Information, reminders, and updates will be communicated to customers through various  channels, including public service announcements, customer alerts, social media updates,  signage at Line 1 stations, and on octranspo.com.

Every effort was made to streamline and coordinate work to minimize customer disruptions.  Should any changes occur, notifications will be provided. OC Transpo thanks customers for their  patience as this work is completed and positive progress is made as we prepare for the opening  of the O-Train East Extension.

OC Transpo understands the disruption that these service adjustments may cause and thanks customers for their ongoing patience as these important works are completed.

Original signed by

Troy Charter

cc: Senior Leadership Team

Transit Services Departmental Leadership Team

Chief Communications Officer, Public Information and Media Relations

 

For You:

Plante Issue Has Roots In Sprung Structure Outcry

Work-From-Home Reduces Employee Respiratory Illness

Free Speech Must Be Honoured By All: PATTON

 

Bookmark The Bulldog, click here




2 Responses

  1. Bruce says:

    Welcome on board the “Occasional” train which is shut down for any and many occasions. Where in North America is there another such transit system? Certainly not a the same cost nor unreliability

  2. Brocklebank says:

    After our earlier experience in which the opening of the Confederation line was accelerated as a result of political pressure, I want testing to be thorough.
    However, I wonder if other transit systems need to close down service multiple times to prepare for a line extension. I was a regular user of the Tokyo subway system for many years and cannot remember shut-downs for system integration similar to the many instances we have had recently. Will we similarly have to close down the system in the future to bring the western extension of the line into service? Is this normal or is it an “only in Ottawa” requirement?