Delays Pile Up On Stage 2 Light Rail
This is a reported presented to the city light-rail subcommittee on Tuesday.
In it, it says the east branch of the project is delayed seven weeks and the west branch is delayed by 17 months.
This from the report:
The East extension is currently forecasting a completion date in Q1, 2025, which is an approximately 7-week delay from the Project Agreement (PA) completion date of November 26, 2024.
On the West extension, from Tunney’s Pasture Station to Moodie and Algonquin stations, the City is currently expecting a delay of up to 17 months against the contractual completion date of May 25, 2025.
The full report from the City of Ottawa is below:
Report English – Quarterly Stage 2 LRT Update
—