Delays Pile Up On Stage 2 Light Rail

 

This is a reported presented to the city light-rail subcommittee on Tuesday.

In it, it says the east branch of the project is delayed seven weeks and the west branch is delayed by 17 months.

This from the report:

The East extension is currently forecasting a completion date in Q1, 2025, which is an approximately 7-week delay from the Project Agreement (PA) completion date of November 26, 2024.

On the West extension, from Tunney’s Pasture Station to Moodie and Algonquin stations, the City is currently expecting a delay of up to 17 months against the contractual completion date of May 25, 2025.

The full report from the City of Ottawa is below:

Report English – Quarterly Stage 2 LRT Update

 —

 

 

advertise.in .your .bulldog

Don’t miss our regular features
Everything Ottawa      Full Local     Bulldog Canadian
Opinion    Comments    Breaking News
Ontario   World    Get Cheap Gas   Big Money
Pop Gossip   Your Home    Relax
Bulldog Weather    Full Local Sports

 

Page 2   Page 3   Page 4   Page 5   Page 6

 

Other features:    Full Bulldog Index    Return to Bulldog Home

Leave a Reply

Your email address will not be published. Required fields are marked *


Paid Content

To read a complete list of all the posts and pages in The Bulldog, click here.
This website uses cookies to improve your experience here. Read More.